Q & A

u

HOW STRONG AND SAFE ARE 3D CONCRETE BUNKERS

M
L
Concrete has been proven over the centuries but “Polymer concrete” is scientifically proven to have over 5 times the tensile strength of Portland cement.
Jo et al. (2006) found that polymer concrete can achieve a very high tensile strength (22.4 MPa in flexural and 7.85 MPa in the splitting test). Whereas Portland cement tensile strength is between 3 to 5 Mpa.
3DBUNKERS has an independent licensed structural engineer who will sign off on each blueprint design before production begins.

WHAT DOCUMENTS WILL I RECEIVE?

M
L
You will receive:

Digital Blueprints in AutoCAD.
High quality two minute SketchUp animation video of your design.
Copies of the Excavator and any survey work orders.
Two reminders (FedEx) letters with a phone call for your print appointment.
Documentation for the air system and warranty documents.

HOW LONG DOES IT TAKE TO BUILD A 3D BUNKER?

M
L
After the hole is excavated, it takes about 2 days to print the bunker. Did you know that all forms of concrete cure more efficiently without oxygen? This means we can cover the bunker with dirt on day 3 and it will cure to its highest possible tensile strength.
If the bunker consists of more than 2 rooms, each additional room can take up to 1 additional day to print. If you have a 5 room bunker, then plan for a 5 to 6 day print.

HOW TO KEEP A SECRET BUNKER A SECRET?

M
L
Honestly, the traditional bunker systems are no secret. In fact, the whole neighborhood can see your metal bunker being lifted into your backyard as a huge crane, whereas 3D bunkers are built in a deep excavated hole with a tent covering the printer.

DO I NEED TO GET A PERMIT TO BUILD A BUNKER

M
L
Unofficially NO but …
There are three common exceptions for not needing a permit.
1. Non-dwelling structures used for recreation that is not connected to the home.
2. The non-dwelling structures are under 14x14ft.
3. The electrical must be off the grid. We have some smart options.
Anyone with common sense would not get a public permit to hide a “secret bunker”. It is up to you if you want to get a permit but just to let you know your secret is out on the Internet. All building permits are public records. If you plan on applying for one, you can describe it as a wine cellar.
When it comes to structural building permits, it seems that 3D architecture is far more advanced and safer than ever before but the local zoning boards across the country are behind times. In simple terms, statewide governmental zoning departments are still out to lunch when it comes to 3D concrete architecture even though hundreds of 3D concrete homes are being built across the U.S.

DOES IT COST EXTRA TO HAVE CURVES AND ARTISTIC DESIGNS?

M
L
No. All our designs have beautiful curves and artistic angles. If you want to do a super dramatic wave or something artistic that requires more polymer concrete, then you just pay a small charge for the extra polymer cement. Our printer injects an accelerant into the polymer which greatly speeds up the cure time and allows us to create a keystone dome which is the strongest form of a roof in the world.

DESIGN DISCLAIMER

M
L
Sometimes people tend to think way too far out of the box, and we would like to reserve the right to deny any design request that could jeopardize the structural integrity of the bunker. All designs are presented in AutoCAD before production.

HOW DO I GET ON THE SCHEDULE?

M
L
Our production calendar is planned very carefully based on location and design requests. One of our staff members will be assigned to your account from beginning to completion. If you would like to proceed with a 3D Bunker, please call our office to see when our production team will be in your area.

WHAT ARE THE BASIC STEPS?

M
L

Before you schedule a conference call, please kindly read our Q&A.
Then proceed to our contact page and email us and a representative will call you within the next 24 hours. Our office will then schedule a 1-hour conference call with you and your representative. The first conference call is to quickly evaluate your design requirements and to answer any questions that were not covered in the Q&A. After your conference call, your representative will email you a contract and details on securing your production date.

When you decide to schedule a 3D Bunker installation, call our office to see what dates are available based on when our development team will be in your area. Dates are filling up quickly due to the threats we are seeing with China, Russia, and Solar flares. As with any company, the date can be taken by another customer so we will give you a 48-hour hold date. This hold date will lock in your date based on your design requirements for 48 hours. This will give you time to make your deposit to Escrow.com and to confirm how many rooms or major features that would extend your production time. You can make changes prior to installation if they don’t extend our scheduled time because we need to keep our appointment with the next customer.

YOU ARE NOW SCHEDULED, WHAT IS NEXT?

M
L
We need to schedule a survey company to mark any underground utilities. We need to look at any blueprints you might have related to the exterior utility outlets.

This is the time to secure any permits. This is up to you and based on how secret you want your bunker to be. Please discuss this with our representative and also please read our contract regarding permits.

Take 10 pictures of your planned bunker area and how a truck can access the area and email them to your assigned representative.

After we have established a safe excavation blueprint/plan to create tunnels and rooms and clear access to your location site, we are ready for phase 2.

We will contract an excavator to remove the dirt approximately 10 days before the 3D printing. They will surround the holes with a protective orange barrier fence.

PRINT DAY

M
L
We will set up the printer and tent and start printing immediately after setup which takes about 3 hours. 1 room bunker and 2 tunnels take about 11 hours to print. Throughout the printing process, we are installing utilities, an air filtration system, proprietary security features, and safe hatches. The next day the excavators will cover the bunker with dirt and gravel.

WHAT ARE SOME OF THE FEATURES?

M
L

With 3D concrete printing, the possibilities are endless.

3D-printed bunk beds are printed up high on the walls.
Shelves for décor or storage space.
Small cubby holes or closet space storage.
Tunnels going to the house or to a secret escape hatch.
A big/tall outdoor fireplace that houses the air filtration intake.
Secret features that we will only disclose to customers.

Watch this clip from an episode of the 1957 The Twilight Zone.

M
L
Do not ever talk about a bunker to your friends even though we would love a referral. Be real and instill some fear in your kids to not ever tell their friends. Do not file any permits unless you claim it to be a wine cellar, fire-safe room, tornado shelter, or something related to your environment. There will be a tent over the printer/bunker and if anyone were to ask what it is, you can say sewer drainage problems. Stinky don’t go back there.

WHAT AMENITIES DO YOU INSTALL OR PROVIDE?

M
L
With all the excitement, it is easy to forget things like a couch. Your bunker is all built and now you wish you had a couch brought in before the roof was installed as it won’t fit through the hatch door.
We have a checklist of what amenities you plan to install or furniture you plan to bring in before the roof is installed or the walls are completed. This is an area that can get complicated due to a lack of planning. Our checklist is very helpful.

WHAT ARE THE COMMON PROBLEMS THAT CAN ARISE?

M
L
You didn’t pay enough attention to our amenity checklist.
Unusual rainfall fills up the excavated hole which we have to pump out the water.
Large boulders slowing down the excavation. That is why we schedule it 10 days before the print.
Extreme bad weather. The tent will 95% take care of that problem.